PlanningDefinition of the usage plans, for a specific period of time, for the available means of production andtransmission, in order to satisfy the energy requirements with respect to quality and continuity of service. and building new power lines and stations are essential to ensuring that the Electricity System adapts to developments in electricity generation and consumption. Terna is committed to searching for technically satisfactory solutions that ensure economic utility for the general public. Specifically, Terna makes sure that the benefit of a development measure in terms of reduced electricity costs for the general public exceeds the costs incurred to implement the measure. Assessment of the environmental repercussions is performed in association with regional and national institutions, according to sustainability and environmental responsibility criteria.

Following the three new power lines that are essential for the country’s development, particularly in the South, that were built in 2006 – Matera-S.Sofia (Basilicata, Campania, Puglia), Turbigo-Rho (Lombardy), Sar.Co (Sardinia), with total investments of 150 million euro – in 2007, Terna strengthened the National TransmissionElectricity transport and transformation activities along the interconnected high- and very high-voltage grid forthe purposes of delivery to customers, distributors, and recipients of self-produced energy. Grid with 210 km of 380 kV(kilovolt=1,000 Volts) unit of measurement of voltage. and 28.8 km of 150/132 kV power lines; nearly 12 km of 150 kV lines were removed. 3 new 150 kV stations were built in Poggio Imperiale, Piscioli (Puglia) and Vicari (Sicily) and 1 new 380 kV station in Gissi (Abruzzo).

Main development activity

In particular, the main works completed during 2007 include:

  • 150 kV Canistro-Morino power line Based on the power that is presently produced and in view of the increased demand expected on the 150 kV grid from the power plants in the area between Avezzano and Popoli, it was necessary to strengthen various lines of the National Transmission Grid in order to allow safely transporting the electricity towards end users.
  • 132 kV Pietrafitta-Attigliano power line Work was carried out to eliminate various interferences with medium voltageRated voltage greater than 1 kV and lower than or equal to 35 kV. lines that prevented exploiting the full transportation load of the 132 kV "Pietrafitta - Baschi" and "Baschi-Attigliano" power lines.

The work carried out in the Molentargius-Saline park was of significant importance. In February 2007, around 12 km of power lines and the 10 pylons in the pond of the "Molentargius-Saline" park, in the province of Cagliari were removed. The spectacular removal of the old power lines, carried out using Elitanker helicopters, was part of the activity plan aiming at upgrading the 150 kV electricity gridA group of plants, lines and stations for transferring electrical energy and supplying the necessary ancillary services. in the Cagliari area. The project includes a wide range of measures aimed at upgrading and improving safety in the territorial Electricity System, considerably reducing the environmental impact caused by the transmission systems. Terna has already built the new “Molentargius-Selargius” buried line (10 km), that allowed pulling down the pylons in the pond.

During 2007, work started to build the submarine DC cable, the SA.PE.I. (Sardinia/Italian mainland), one of the most important strategic projects planned by Terna to upgrade Italy's Electricity System. It will be a truly record-breaking cable: a 420 km submarine connectionThe group of Grid elements forming the transmission line, and the bays at the borders of the same, includingthe related circuitry isolating apparatuses. Connections are classified by voltage level with reference to ratedvoltage. The length of the connection is generally the length of the line which forms the connection itself.Connection lineAny power line that links the power distribution plant with the user’s plant, or the power distribution plant with the connection station., which will connect to Latina, laid at a depth of 1,600 meters below sea level – the deepest in the world – with an overall investment of 650 million euro.

MAIN WORKS INCLUDED IN THE 2008 DEVELOPMENT PLAN

Image

Connection of new power systems

Access to the grid infrastructure is regulated by the Italian Authority for Electricity and Gas (AEEG). Individual solutions are established by Terna on the basis of the importance of the power stationThe part of a grid which is concentrated and closed in a specified site, and used for switching electrical energyamong the lines of a grid, for transferring the electrical energy between grids with different levels of voltage,and for transforming the electrical energy to the lowest voltage usable by the user. and of its impact on the operationThe methodical use of power plants and accessories according to procedures codified in the implementationof the decisions regarding the operation of the Grid. Operation includes:• the running of the plants in order to carry out Terna’s orders and autonomous deliveries; • emergency assistance following fault or anomalies; • operations for going offline and for the security of the plants; • the monitoring of the status of the plants; • plant inspections. of the Electricity System. An essential part of the Grid Code is the description of typical connection solutions. However, Terna can evaluate alternative solutions, but these must be approved by the AEEG to minimize the possibility of decisions that could appear discriminatory to applicants.

The current rules govern many phases of the process of accessing the grid infrastructure and define Terna’s margins of discretion, such as timescales for dealing with applications, determination of the components of the technical solutions for connection, and average timescales and costs of implementation. Terna meets these requirements by using an IT system to manage connection applications, which allows applications to be uniquely coded and traced and so guarantees the transparency of the process. In 2007, grid plant building operations were completed for the connection of:

  • 9 primary distributionThe transport and transformation of electrical energy on high-, medium- and low-voltage distribution grids forsupply to the final customers. cabins;
  • 4 traditional source power systems;
  • 6 renewable source power systems;
  • 1 substation for supplying power to the railway network;
  • 1 electricity station.

Highlight: High voltage direct current - hvdc